–An engineering, procurement and construction contract under which one contractor designs, procures and builds a complete facility for a fixed price and by a fixed date, and hands it over ready to operate

EPC stands for engineering, procurement and construction. Under an EPC contract, the contractor takes single-point responsibility for the whole project: it designs the facility, buys the equipment and materials, builds it, tests it and hands it over in working order. The owner states what it needs in the Employer’s Requirements, and the contractor decides how to deliver it. EPC contracts are also called turnkey contracts, because the owner should only have to turn the key to start operations.

In the UAE, EPC contracts are the standard structure for power plants, desalination plants, solar and wind projects, oil and gas facilities and large industrial plants. Owners and their lenders want cost and time certainty, and the EPC model gives it by placing the bulk of the risk on the contractor. The contractor prices that risk into a higher lump sum.

  • One contractor is responsible for everything. Design, procurement, construction, testing and commissioning rest with a single party, so the owner has one counterparty for defects and delay.
  • The price is a fixed lump sum. The contract price changes only for the events the contract allows, such as variations ordered by the owner.
  • The completion date is fixed. Late completion triggers delay liquidated damages, subject to extensions of time for the events the contract recognises.
  • Performance is guaranteed. The contractor guarantees output, efficiency or other performance levels, tested before handover and backed by performance liquidated damages.
  • FIDIC’s Silver Book is the reference form. The FIDIC Conditions of Contract for EPC/Turnkey Projects, known as the Silver Book, is the standard form from which EPC contracts in the region start.
  • UAE law adds its own rules. The Civil Code gives courts power to adjust liquidated damages and imposes ten-year decennial liability that the contract cannot exclude.

Who this applies to

This applies to developers, project companies and government-related owners procuring energy, utilities, industrial and infrastructure projects in the UAE, and to the EPC contractors, consortium members and equipment suppliers bidding for them. It also concerns lenders and their advisers reviewing EPC contracts for bankability. The model is used across energy and construction projects.

Our construction lawyers in Dubai draft and negotiate EPC contracts for owners and contractors, advise on bankability for project finance, and act in the disputes that follow. This article explains how EPC contracts work. Our article on EPC contract disputes in UAE energy projects covers claims, performance disputes and arbitration.

The legal framework

  • The EPC contract and its standard form. The contract itself allocates risk, sets the price and the completion date, and chooses where disputes are decided. Large UAE EPC contracts are based on the FIDIC Silver Book, heavily amended by Particular Conditions.
  • Federal Decree-Law No. 25 of 2025 issuing the Civil Transactions Law. The new Civil Code applies to contracts concluded from 1 June 2026. Its chapter on contracts for work, Articles 812 to 839, governs construction contracts, including decennial liability in Article 821, hardship in Article 829(3) and termination in Article 836.
  • Federal Law No. 5 of 1985, the former Civil Code. It continues to govern EPC contracts concluded before 1 June 2026.
  • Procurement rules of the owner. Government and utility owners such as EWEC in Abu Dhabi and DEWA in Dubai tender independent power and water projects, and their project documents shape the EPC terms the developer can accept.

The administering bodies:

  • The project owner and its engineer. They administer the contract, review the design, witness tests and issue the taking-over certificate.
  • The lenders and their technical adviser. On financed projects, they review the EPC contract, monitor progress and hold step-in rights.

The supervising courts:

  • Arbitral tribunals and the courts. EPC disputes go to arbitration under the DIAC rules, arbitrateAD or ICC rules, and the onshore courts or the DIFC and ADGM Courts supervise the arbitration and enforce the award.

EPC, EPCM and design-bid-build

The EPC model is one of several ways to deliver a project. The choice decides who carries design, cost and interface risk.

Design-bid-build

The owner appoints a designer, completes the design and then tenders the construction to a contractor that builds to the owner’s design. The owner carries the design risk and the risk of gaps between design and construction. FIDIC’s Red Book is written for this model.

Design and build

The contractor designs and builds to the owner’s requirements, but the owner keeps more risk than in an EPC contract, including risk of unforeseeable ground conditions. FIDIC’s Yellow Book is written for this model, and an engineer administers the contract on the owner’s behalf.

EPCM

Under an engineering, procurement and construction management contract, the EPCM contractor designs the project and manages procurement and construction on the owner’s behalf, but it does not build. The owner signs the construction and supply contracts directly and carries the cost and interface risk. The EPCM contractor is paid a fee and is liable only for the quality of its own services.

Note: UAE projects also use hybrid structures, such as split onshore and offshore EPC contracts or an EPC contract with owner-supplied equipment. The allocation in each case depends on the drafting rather than the label.

How an EPC contract allocates risk

The EPC model places on the contractor almost every risk that the owner does not expressly keep. The Particular Conditions then move some of those risks back.

Design and fitness for purpose

The contractor is responsible for the design and for the facility being fit for the purposes in the Employer’s Requirements. Under the Silver Book, the contractor also takes responsibility for the accuracy of the Employer’s Requirements, with narrow exceptions. A contractor that relies on owner data without checking it bears the consequences of errors.

Site and ground conditions

Under the Silver Book, the contractor takes the risk of unforeseeable difficulties, including ground conditions, unless the contract states otherwise. This is the sharpest difference from the Yellow Book. Contractors bidding for UAE projects should price ground risk or negotiate a reallocation where site data is limited.

Owner’s risks

The owner keeps the risks the contract names, such as its own delays, variations it orders, changes in law and defined exceptional events. Everything else stays with the contractor. The list of owner’s risks is where negotiation of an EPC contract concentrates.

Core clauses in a UAE EPC contract

Lenders and owners review the same clauses on every project. These are the terms that decide whether an EPC contract is bankable and whether a contractor can price it.

Price and payment

The contract price is a lump sum, paid against milestones or a payment schedule. An advance payment, secured by an advance payment guarantee, funds early procurement. Retention may be deducted from each payment and released at taking over and at the end of the defects period.

Completion and delay damages

The contractor must complete by the time for completion, with extensions only for the events listed in the contract and on time-barred notice. Late completion triggers delay liquidated damages at a daily or weekly rate, capped at a percentage of the contract price. Lenders size the delay damages to cover debt service and fixed costs during the delay.

Tests and performance guarantees

Before taking over, the facility must pass tests on completion. The contractor guarantees performance levels such as output, efficiency, heat rate or water production. A shortfall within an agreed band leads to performance liquidated damages. A shortfall beyond a minimum level allows the owner to reject the facility.

Liability caps and exclusions

The contractor’s total liability is capped, at a percentage of the contract price or at the price itself, with separate sub-caps for delay and performance damages. Indirect and consequential losses are excluded. Caps do not apply to fraud, wilful misconduct and other excluded matters, and they cannot limit decennial liability under UAE law.

Security

The contractor provides a performance bond, an advance payment guarantee and, where the contractor is a subsidiary or a consortium, parent company guarantees. Consortium members are jointly and severally liable to the owner. Our article on liquidated damages in the UAE covers how courts treat agreed damages.

Taking over and defects liability

The owner takes over the facility when it passes the tests and the conditions in the contract are met. The contractor then remains responsible for remedying defects during a defects notification period, of one to two years on a standard project, with possible extensions for repaired parts.

Variations

The owner may order variations to the scope, and the contractor is entitled to adjustment of the price and time. Disputes arise over changes the owner did not formally instruct. Our article on FIDIC and bespoke contracts in the UAE covers how amendments shift these risks.

Termination

The owner may terminate for contractor default and, under the standard forms, for convenience with compensation. The contractor may terminate or suspend for non-payment and prolonged suspension. On financed projects, lenders receive step-in rights through a direct agreement with the contractor.

Talk to us

Negotiating an EPC contract in the UAE?

Kayrouz & Associates drafts and negotiates EPC contracts for owners and contractors and reviews them for project finance bankability.

This issue also concerns Arbitration and Corporate & Commercial Law.

What UAE law adds to an EPC contract

An EPC contract governed by UAE law is a contract for work under the Civil Code. Several mandatory rules apply whatever the contract says. For contracts concluded from 1 June 2026, they are found in the new Civil Code. Our concordance of old and new Civil Code article numbers maps the provisions.

Adjustment of liquidated damages

Under Article 340 of the new Civil Code, which replaced Article 390 of the 1985 code, a court or tribunal may adjust agreed compensation to match the actual loss. A contractor can ask for delay or performance damages to be reduced where they exceed the owner’s loss. Published analyses report that the new code narrows the owner’s ability to have damages increased.

Decennial liability

Under Article 821, which replaced Article 880, the contractor and the supervising engineer are jointly liable for ten years. The liability covers total or partial collapse of the works and defects that threaten their stability or safety. A clause that excludes or limits this liability is void. EPC contractors cannot cap it, and they should consider how it interacts with insurance and subcontracts. Our article on decennial liability for contractors and engineers covers the regime.

Hardship in construction contracts

Article 829(3) applies where unforeseeable general exceptional circumstances disrupt the contract’s balance and undermine the basis of its financial assessment. A court may then extend the time for completion, adjust the price or rescind the contract. The 1985 code had no equivalent provision. EPC owners relying on a fixed lump sum should take this power into account.

Force majeure and termination

Under Article 236, impossibility of performance extinguishes the corresponding obligations. Under Article 836, the owner may terminate a contract for work for convenience, with compensation to the contractor. The contract’s own force majeure and termination clauses operate alongside these rules.

Dispute resolution in EPC contracts

EPC disputes are technical and expensive, and the contract sets a staged procedure to resolve them.

The Dispute Avoidance and Adjudication Board

The 2017 FIDIC forms provide for a Dispute Avoidance and Adjudication Board (DAAB) to give decisions that bind the parties unless revised in arbitration. Under the Silver Book, the DAAB is appointed when a dispute arises, unless the parties agree a standing board. UAE parties sometimes delete the DAAB, which removes an early route to resolve disputes during the works.

Arbitration

Arbitration under DIAC, arbitrateAD or ICC rules is the standard final route for UAE EPC contracts. The seat decides which courts supervise the arbitration and enforce the award. Owners and contractors should align the dispute clauses in the EPC contract, the subcontracts and the project documents so that related disputes can be heard together.

Common mistakes in UAE EPC contracts

Signing the Silver Book without reading the Particular Conditions. The amendments decide the real risk allocation, and the standard form is only the starting point.

Accepting ground risk without site data. Under the Silver Book, unforeseeable ground conditions fall on the contractor unless the contract moves them back.

Setting caps that conflict with UAE law. A cap that purports to limit decennial liability is void, and agreed damages remain open to adjustment.

Mismatching the EPC contract and the project documents. Completion dates, performance levels and damages that do not align with the power or water purchase agreement leave a gap the owner must fund.

Treating subcontracts as back-to-back without checking them. A contractor that gives the owner more than it receives from its suppliers carries the difference. Our article on risk allocation in UAE energy subcontracts covers this gap.

Citing the wrong Civil Code. Contracts concluded from 1 June 2026 fall under the new code, and drafting that still cites the 1985 articles invites argument.

What owners and contractors should do next

  • Choose the delivery model deliberately. Decide between EPC, EPCM and design-bid-build based on who should carry design, cost and interface risk.
  • Review the Employer’s Requirements. Make the requirements complete and measurable, and agree who carries the risk of errors in them.
  • Align with the project documents. Match completion dates, performance levels and damages to the offtake and finance agreements.
  • Size the damages and caps. Set delay and performance damages and liability caps that the owner needs and the contractor can price.
  • Check the UAE mandatory rules. Confirm how decennial liability, adjustment of damages and hardship affect the contract.
  • Settle the dispute route. Keep the DAAB, choose the arbitral rules and seat, and align the dispute clauses across the project.

How do EPC contracts work in the UAE?

An EPC contract in the UAE makes one contractor responsible for engineering, procurement and construction of a complete facility, for a fixed lump sum and by a fixed date. The contractor guarantees performance, pays liquidated damages for delay and shortfall, and takes the bulk of project risk, including design and, under the Silver Book, unforeseeable ground conditions. The owner gains cost and time certainty, which is why the model dominates UAE energy, utility and industrial projects.

The main difference from EPCM and design-bid-build is who carries the risk. Under EPC it rests with the contractor. Under EPCM and design-bid-build it stays with the owner, which signs the construction contracts and manages the interfaces.

The commercial consequence is that UAE law shapes the bargain. Courts can adjust agreed damages under Article 340 of the new Civil Code, decennial liability under Article 821 cannot be excluded, and Article 829(3) allows rebalancing for exceptional events. Owners and contractors that negotiate with these rules in mind sign contracts that hold up when the project is tested.

For owners, contractors and lenders, our construction law team advises on EPC contract structuring, negotiation and bankability, and on the disputes that arise during construction and performance testing.

‍