Every Request for Arbitration filed with the Dubai International Arbitration Centre since 21 March 2022 follows the DIAC Arbitration Rules 2022, whatever date the contract was signed. This article explains how a DIAC case starts, how the tribunal is formed, the deadline for each stage, and which court supervises the final award.

How long does a DIAC arbitration take under the 2022 Rules?

–The tribunal must issue its final award within six months of receiving the case file, unless the parties or the DIAC Arbitration Court extend that period

Article 35.1 of the DIAC Arbitration Rules 2022 counts the six months from the date the Centre transmits the file to the tribunal. Transmission follows the constitution of the tribunal, and the Arbitration Court appoints no arbitrator until the advance on costs is paid. The weeks before transmission therefore matter as much as the six months after it.

  • The case starts on receipt. Under Article 4.6, the arbitration commences on the date DIAC receives a complete Request for Arbitration with the USD 3,000 registration fee.
  • The respondent has 30 days. The Answer is due within 30 days of notification of the Request under Article 5.1, and the Centre may extend that deadline by up to 10 days.
  • One arbitrator is the default. Where the parties have not agreed a number, Article 10 provides for a sole arbitrator unless the Arbitration Court decides that three members are appropriate.
  • Unpaid deposits stop the case. A claim whose share of the advance on costs remains unpaid after a final deadline set by the Arbitration Court is treated as withdrawn.
  • Smaller claims move faster. Claims of AED 1,000,000 or less go to the expedited procedure under Article 32, with a final award due within three months of transmission of the file.
  • The seat decides the court. Where the parties have not chosen a seat, Article 20.1 makes the DIFC the initial seat, which places any challenge to the award before the DIFC Courts.

Who this applies to

This article is for general counsel, finance directors and founders of companies facing a dispute under a contract with a DIAC arbitration clause, as claimant or as respondent. It also concerns companies whose older contracts referred disputes to the DIFC-LCIA or the Emirates Maritime Arbitration Centre. Construction and real estate disputes made up half of the cases DIAC administered in 2025, and DIAC clauses also appear in energy and maritime and logistics contracts.

DIAC registered 312 cases in 2025, with USD 3.8 billion in dispute and parties from 60 countries, according to its 2025 casework figures. Our arbitration lawyers in Dubai act for claimants and respondents at every stage of a DIAC case. Companies still choosing an institution for a new contract will find that decision in our comparison of DIAC and ICC arbitration for construction disputes and our DIAC and arbitrateAD clause checklist.

The legal framework

A DIAC arbitration is governed by the DIAC Rules and fee table, the Dubai decree that created the current centre, and the arbitration law of the seat.

  • DIAC Arbitration Rules 2022. The 2022 Rules entered into force on 21 March 2022 and govern every Request submitted after that date.
  • DIAC Table of Fees and Costs 2025. The 2025 table applies to cases registered from 1 January 2025 and fixes the registration, administrative and tribunal fees.
  • Dubai Decree No. 34 of 2021. In force from 20 September 2021, Decree No. 34 abolished the Emirates Maritime Arbitration Centre and the DIFC Arbitration Institute and transferred their cases to DIAC.
  • Federal Law No. 6 of 2018 on Arbitration. The UAE Arbitration Law, amended by Federal Decree-Law No. 15 of 2023, governs arbitrations seated onshore.
  • DIFC Law No. 1 of 2008. The DIFC Arbitration Law governs DIFC-seated cases. On 11 June 2026, the DIFC Authority published proposals that would replace it with an Arbitration and Mediation Law of 2026, which has not been enacted.

The administering and supervising bodies:

  • DIAC Arbitration Court. Appoints every arbitrator, decides challenges, extends time limits and reviews the form of draft awards.
  • The Centre. Registers each Request, notifies the parties, collects the advance on costs and transmits the file to the tribunal.
  • Dubai Courts. Supervise arbitrations seated onshore in Dubai, hear applications to set awards aside and ratify awards.
  • DIFC Courts. Supervise DIFC-seated arbitrations, including every DIAC case where the parties chose no seat.

How a DIAC arbitration starts

Under Article 4 of the DIAC Arbitration Rules 2022, the claimant starts the case by filing a Request for Arbitration with the Centre and paying the registration fee at the same time.

The Request identifies the parties, attaches the contract containing the arbitration clause and describes the dispute briefly. It also states the relief sought, an estimate of the sum claimed, the claimant's position on the number of arbitrators, and the seat and language. Under Article 4.4, the Centre will not register a Request filed without the fee. The 2025 Table of Fees and Costs sets that fee at USD 3,000, of which USD 1,500 is credited towards the claimant's share of the advance on costs.

Article 4.6 treats the date the Centre receives a complete Request as the date the arbitration commenced. That date matters for limitation periods, so a claimant close to a limitation deadline should file every required document with the Request.

Contracts that still name the DIFC-LCIA

Decree No. 34 of 2021 transferred the rights and obligations of the DIFC Arbitration Institute and the Emirates Maritime Arbitration Centre to DIAC. A claimant under one of those older clauses therefore files with DIAC. The Dubai Media Office confirmed that the Dubai Courts and the DIFC Courts continue to hear applications in cases from the abolished centres. Companies should still amend those clauses to name DIAC before a dispute arises.

What the respondent must file within 30 days

Under Article 5.1, the respondent must file its Answer within 30 days after the Centre notifies it of the Request.

The Answer responds to the claim and states the respondent's position on the seat, the language and the number of arbitrators. Where the clause provides for three arbitrators, it also nominates the respondent's arbitrator. The Centre may extend the deadline by up to 10 days under Article 5.7, so a respondent that needs more time should apply before the 30 days expire.

A counterclaim may be filed with the Answer or later, and Article 5.5 requires its registration fee within 7 days of filing. A respondent that objects to jurisdiction should raise the objection in the Answer. Under Article 4(1) of Federal Law No. 6 of 2018, the person who signs an arbitration agreement must have authority to agree to arbitration for the company. A respondent that takes part in the case without objecting may lose the right to raise that point later.

How the tribunal is formed

Under Article 12.1 of the DIAC Arbitration Rules 2022, the Arbitration Court appoints every arbitrator, including those the parties nominate.

One arbitrator or three

Article 10 allows the parties to agree any number of arbitrators, provided the number is odd. Where they have not agreed, the tribunal is a sole arbitrator unless the Arbitration Court decides that three members are appropriate. A clause that calls for two arbitrators conflicts with the odd-number requirement and invites an early dispute about the tribunal itself.

Nominations and deadlines

For a sole arbitrator, the parties may nominate jointly within the time allowed, failing which the Arbitration Court appoints. Article 13 offers a list procedure instead, in which the Centre sends at least three names and each party has 7 days to rank them. For a three-member tribunal, each party nominates a co-arbitrator, and the two co-arbitrators have 10 days to agree the chair. Under Article 12.7, a party that fails to nominate in time waives the right irrevocably and the Court appoints in its place.

Challenging an arbitrator

Each arbitrator signs a declaration of acceptance, impartiality and independence before appointment under Article 14.2, and the duty to disclose continues for the whole case. Under Article 15.2, a party must file any challenge within 15 days of notification of the appointment, or within 15 days of learning the grounds.

What the advance on costs means for each party

Under Appendix I of the DIAC Arbitration Rules 2022, the parties pay the advance on costs in equal shares, and the advance covers the tribunal's fees and expenses and the Centre's administrative fee.

The 2025 table calculates both amounts from the sum in dispute, and the Arbitration Court fixes them itself where the sum exceeds USD 100,000,001. DIAC publishes a cost calculator that estimates both from the disputed amount in AED. Under Article 12.8, no arbitrator is appointed until the advance is paid in full. Under Article 34.7, the Centre releases the signed award only after payment.

Where a respondent refuses to pay its half, Article 3.3 of Appendix I allows the claimant to pay that share and recover it through an award on costs. If a share remains unpaid, Article 3.4 requires the Arbitration Court to set a final deadline, after which the relevant claim or counterclaim is treated as withdrawn.

The DIAC timetable at a glance

The DIAC Arbitration Rules 2022 fix a deadline for most steps between the Request and the final award.

Note: Deadlines counted from transmission of the file start only after the tribunal is constituted, and no arbitrator is appointed until the advance on costs is paid in full. The parties or the Arbitration Court may extend both award deadlines.

From the preliminary meeting to the final award

Under Article 23.1, the tribunal must contact the parties to fix a preliminary meeting no later than 15 days after the Centre transmits the file.

The procedural timetable

After consulting the parties, the tribunal fixes the timetable for written submissions and documents under Article 23.3. Each extra round of submissions or document requests adds legal fees and weeks to the case. A party that wants a shorter case should propose fixed dates and limits on document production before the meeting.

Seat and language

Article 20.1 makes the DIFC the initial seat where the parties have not agreed one, and the tribunal may decide the seat finally after hearing the parties. Under Article 21.1, the initial language is the language of the arbitration agreement, so an English-language contract leads to an English-language arbitration unless the parties agree otherwise.

Review of the draft award

Under Article 34.5, the tribunal must submit its draft award to the Arbitration Court at least 30 days before the award deadline. The Court reviews the form of the draft for compliance with the Rules and fixes the tribunal's final fees, and leaves the decision on the merits to the tribunal.

The award also fixes the costs of the arbitration, which under Article 36.1 include the fees of each party's legal representatives. Our article on recovering legal costs in UAE arbitration covers that point in detail. Article 38 requires the parties and the tribunal to keep the award and the case materials confidential, subject to the exceptions listed in the Rules.

Faster routes for smaller or urgent claims

Article 32.1 of the DIAC Arbitration Rules 2022 applies the expedited procedure where the claim and any counterclaim total AED 1,000,000 or less, excluding interest and legal costs.

The parties can also agree in writing to use it for a larger claim, and the Arbitration Court can apply it in cases of exceptional urgency. The Centre aims to appoint a sole arbitrator within 5 days of the Court's decision, and the final award is due within 3 months of transmission of the file under Article 32.5.

The emergency arbitrator

A party that needs urgent relief before the tribunal exists can apply for an emergency arbitrator under Article 2 of Appendix II. The Centre seeks to appoint the emergency arbitrator within 1 day of receiving a compliant application, and the emergency arbitrator must set a timetable within 2 business days. The 2025 table charges a separate USD 3,000 registration fee for the application.

Interim relief under Appendix II includes orders to preserve assets or evidence and security for costs, which can cover legal fees. Our article on interim measures in UAE arbitration compares relief from the tribunal with relief from the courts.

Multi-party cases and funded claims

The DIAC Arbitration Rules 2022 allow consolidation of related arbitrations under Article 8 and joinder of additional parties under Article 9, and Article 22 requires disclosure of third-party funding.

The Arbitration Court decides on joinder and consolidation before any arbitrator is appointed, and the tribunal decides after it is constituted. Consolidated cases merge into the arbitration that commenced first, unless the clause excludes consolidation under Article 8.9. For a contractor with claims under a main contract and several subcontracts, consolidation can avoid parallel cases and inconsistent awards.

Under Article 22.1, a funded party must disclose the funding promptly to the other parties and the Centre, name the funder and state whether the funder will pay adverse costs. Under Article 22.3, the tribunal may take that commitment into account when it divides the costs of the arbitration.

Talk to us

Facing a DIAC claim or preparing to file one?

Kayrouz & Associates acts for claimants and respondents in DIAC arbitrations. Speak to us before the 30-day Answer deadline or the first nomination falls due.

This issue also concerns construction law and litigation and dispute resolution.

Which court supervises a DIAC award

The seat of a DIAC arbitration decides which court hears an application to set the award aside. The Dubai Courts supervise an onshore Dubai seat, and the DIFC Courts supervise a DIFC seat.

For an onshore seat, Article 54 of Federal Law No. 6 of 2018 allows a party to apply to set the award aside within 30 days of notification. The winning party seeks ratification of the award from the court of appeal under Article 55. For a DIFC seat, the DIFC Arbitration Law allows three months to challenge the award. The DIFC Authority's June 2026 proposals would shorten that period to 30 days, but they are not yet law.

Our guides on time limits to challenge or enforce an arbitral award in the UAE and on enforcing a DIFC-seated award onshore cover the court stage. Where the losing party has assets outside the UAE, the winning party can enforce the award under the New York Convention, which the UAE joined in 2006.

Common mistakes in DIAC cases

Filing an incomplete Request. The arbitration commences only when DIAC receives a complete Request with the fee, so missing documents can move the commencement date past a limitation deadline.

Missing the nomination window. Under Article 12.7, a party that fails to nominate in time waives the right irrevocably, and the Arbitration Court chooses that arbitrator.

Leaving the seat unstated. A clause with no seat makes the DIFC the initial seat under Article 20.1, and the supervising court may then differ from the one the parties expected.

Leaving a share of the advance unpaid. After the final deadline set by the Arbitration Court, the unpaid claim or counterclaim is treated as withdrawn under Article 3.4 of Appendix I.

Disclosing funding late. Article 22.1 requires prompt disclosure of a funder, and the tribunal may consider the funding when it allocates costs.

What a party to a DIAC dispute should do next

  • Check the clause and the seat. Confirm the institution, the seat, the number of arbitrators and the language, because each one determines a step in the procedure.
  • Record every deadline on receipt. Diary the 30-day Answer date, the 15-day challenge window and the 7-day counterclaim fee date as soon as the Request arrives.
  • Budget for the advance on costs. Use the DIAC cost calculator to estimate your share, since no arbitrator is appointed until the advance is paid in full.
  • Choose an arbitrator candidate early. Complete conflict checks before the nomination deadline, since a missed nomination passes the choice to the Arbitration Court.
  • Disclose any funding promptly. Tell the Centre and the other parties about a third-party funder as soon as the arrangement is signed.
  • Decide whether you need urgent relief. Apply for an emergency arbitrator where assets or evidence are at risk before the tribunal is formed.

How does a DIAC arbitration work under the 2022 Rules?

A DIAC arbitration under the 2022 Rules starts when the Centre receives a complete Request and the registration fee. It ends with a final award due within six months of the tribunal receiving the file, after a 30-day Answer period and appointments made by the Arbitration Court.

The advance on costs decides when the six-month period begins, because the Arbitration Court appoints no arbitrator until it is paid in full. A respondent that refuses to pay its share can delay the tribunal, and the claimant must then decide whether to pay that share and recover it later.

Each missed step has a commercial cost. A late nomination passes the choice of arbitrator to the Arbitration Court, and an unpaid share can lead to a claim being treated as withdrawn. For an onshore seat, a missed 30-day window under Federal Law No. 6 of 2018 ends the right to ask the Dubai Courts to set the award aside.

For companies bringing or defending a claim before DIAC, our arbitration team in Dubai advises on Requests and Answers, tribunal appointments and challenges, and the enforcement or annulment of DIAC awards.

Let’s talk
Your success starts with the right guidance.

Whether it’s business or personal, our team provides the insight and guidance you need to succeed.